CURRENT WORK
The Timpanogos Special Service District (TSSD) is installing an additional sewer line along the south side of 7350 North/145 North between Saratoga Road and Center Street in Lehi.
This area is an active construction zone and the current closure segment is closed to ALL vehicle traffic, bicyclists and pedestrians.
The intersection of Saratoga Road and 7350 North/145 North is currently closed and is anticipated to open as soon as October 9. This closure is necessary to install the sewer structure box on the west end of the project limits. The existing closure of 7350 North/145 North between 9150 West and Saratoga Road will remain closed to vehicles and pedestrians during this work (residential access to homes on 7350 North/145 North closest to Saratoga Road will be maintained).
Traffic will be detoured from Saratoga Road to Bearing Drive to Northshore Drive.
​
Vehicles are advised to follow the traffic detours that are in place and expect delays during peak hours (including school pick-up and drop-off times). The construction area contains open trenches, making the road impassable to traffic and dangerous for bicyclists, pedestrians and school children navigating the area. All bicyclists and pedestrians are encouraged to use the Utah Lake Parkway Trail south of 7350 North/145 North as an alternative (see map below).

.png)
Construction schedules are weather-dependent and subject to change.
ADDITIONAL PROJECT INFORMATION
7350 North/145 North and Center Street in Lehi is anticipated to open as early as Wednesday, Sept. 13. Crews have completed preliminary waterline and utility work in the area.

FUTURE SECTION CLOSURES
Additional closures of 7350 North/145 North will take place throughout the project, until summer 2024. Emails will continue to be sent out with future closure information. Each closure will be conducted in sections that have designated detour routes so drivers can maintain access to the community and local schools. Click the button below to view the section closures and detour routes that will be implemented throughout the project.
SURVEY WORK
As part of the Westside Interceptor project, crews are conducting survey work in your area. Work may include:
-
Marking elevation levels on home foundations 
-
Staking property and utility lines 
Please do not remove any stakes, paint or other identifiers made to your property. If you have questions about the work being conducted, please call a project representative at 385-999-1929. 
​
OTHER WORK
-
Locating utilities​​
-
Removing surface water
-
Removing fencing
-
Clearing and grubbing
​
For questions on the current work and traffic configurations, please call 385-999-1929.